the overall process
Generally speaking, the order of events for a major remodeling project will go something like this.
After you’ve made all of your choices and have the installation specifications for the products and materials you will use, you will need to discuss the schedule with your designer and/or contractor. They will change the installation order based on the lead times and specifications on various materials.
A typical schedule would start with a complete tear-out, any structural modifications, installation of windows and doors, plumbing modifications, electrical modifications, drywall, tape and texture, painting, floor and underlayment (particle board), cabinet installation, countertops, plumbing and electrical top-out, floor covering installation, and appliance installation, followed by a grand dinner party.